Hastings PFAS Water Plants Update: $5 Million Grant, New Inspectors and a Late Delivery
TLDR
- Hastings locked in a $5 million state grant for its eastern PFAS water plant.
- The council hired WSB for up to $1,079,834 to oversee building it. The grant covers that.
- The central plant is behind schedule because its filter tanks are late. It should still be done in spring.
- Expect one more day of one-lane closures on North Frontage Road in early November.
For the first time since the original planning study, all three of Hastings' PFAS water plants had news at the same meeting. City Administrator Dan Wietecha said so himself at the Nov. 2 Hastings City Council meeting. Here's where each one stands, and what it means for your tap water.
Quick Refresher
PFAS are the "forever chemicals" that got into Hastings' groundwater. To clean them out, the city is building three treatment plants: central, eastern and western. The latest construction estimate is $70.3 million, plus more than $1 million a year to run them, according to the city. Grants, a 3M settlement and our water bills are paying for it.
Eastern Plant: $5 Million Is Locked In
The council approved a $5 million grant agreement with the Minnesota Public Facilities Authority (a state agency that helps cities pay for water projects). It comes from the state's emerging contaminants program.
Public Works Director Ryan Stempski said this one took a lot of back and forth since July. "We have crossed the finish line," he said.
Why it matters: Rice Lake Construction Group just signed on to build the eastern plant. That $5 million gets crews started. It bridges the gap until a bigger $17.5 million state bonding grant comes through. Wietecha said that one is probably two or three months out.
Council Member Angie Haus made the motion. Council Member Dave Pemble seconded. It passed with no "no" votes.
Eastern Plant: WSB Will Watch the Build
Next, the council hired WSB for construction support. That means soil testing, surveying, staking, inspections and being the city's go-between with the builder. WSB is already doing the same job at the central plant, so it's the same team.
Own a local south metro business?
We help Dakota & Scott County businesses reach local readers. Takes 30 seconds.
Thanks β enjoy the read! π
The contract is for up to $1,079,834. Stempski said that matches the amount in the grant agreement "every penny," so the state pays it back. Council Member Tim Lawrence moved it, and Council Member DawnMarie Vihrachoff seconded.
There's one more piece. The city will run water mains up to the Minnesota Veterans Home property line near the eastern plant. The state will hook up the inside. It'll also seal the home's old wells and retire its water towers. That work is planned for 2027.
Central Plant: Moving, But Running Late
The central plant at 1290 North Frontage Road is the furthest along. Here's what builder Magney got done last month:
- Roofing and masonry are done.
- Most windows and floor slabs are in.
- In late October, crews tied into the water mains on North Frontage Road.
North Frontage Road was closed Oct. 19 to 30 for that work. Next up is one more day of one-lane closures in early November while crews lay temporary asphalt to get through winter. That helps with plowing and driving. Curb, gutter and drainage work happens in spring.
Now the not-so-great part. The plant needs 12 big filter tanks. Only the first 2 showed up in October. The rest will arrive in pairs every couple of weeks through the end of the year. Wietecha said that will push back when the plant is "substantially complete." But final completion is still expected in spring 2027.
Western Plant: Land Deal Done
Earlier that same night, the council approved buying 3.14 acres in Sunset Hills off 15th Street for $700,000. That's the new home for the western plant, instead of Wallin Park.
Wietecha also shared the state's draft funding ranking. The western plant tied at No. 25 this year. It tied at No. 17 last year. He said more cities just sent in strong projects. That ranking matters for grants.
The Bottom Line
Real progress, with a few speed bumps. The $5 million grant is a big deal because it keeps the eastern plant from stalling while the city waits on the state. The late filter tanks at the central plant are annoying, but spring is still the target.
If you're wondering why your bill keeps climbing, this is why. We broke down the 2026 Hastings water rate increase and why your water bill is going up. Catch up on the $15.3 million eastern plant contract too. For official info, check the city's water treatment plant projects page, the Minnesota Public Facilities Authority and the Hastings Star Gazette's coverage of plant funding.
Frequently Asked Questions
When will the central water plant in Hastings be done?
Final completion is still expected in spring 2027. Late filter tanks will push back some steps, but the city hasn't changed the spring target.
Is North Frontage Road closing again?
Not fully. Expect one day of one-lane closures in early November while crews put down temporary asphalt for winter. Permanent curb and drainage work comes in spring.
What is the $5 million grant for?
It helps pay to build the eastern PFAS plant. It comes from the Minnesota Public Facilities Authority's emerging contaminants program.
Who is WSB and why are we paying them?
WSB is an engineering firm. It'll test soil, survey, inspect and work with the builder on the eastern plant. The state grant pays back the cost.
Is the Veterans Home getting city water?
Yes. Hastings will run water mains to the Minnesota Veterans Home property line in 2027. The state will handle the hookups inside and close its old wells.