Lakeville's New Data Center Rules: No Water Cooling, No Campuses, Tighter Noise Limits
TLDR
At the Nov. 16 Lakeville City Council work session, the city rolled out its revised data center rules. This is the draft council paused in August so more residents could weigh in. And honestly? It shows. The new Lakeville data center ordinance is a lot stricter, and every resident who spoke thanked the city for it.
First, Nobody Has Applied
Community Development Director Tina Goodroad started with this. Lakeville doesn't have a data center application. It doesn't have a proposal. It never has. This is the city setting rules before anyone shows up.
That matters. Council Member Dan Wolter said this all started about a year ago at a National League of Cities conference. Other cities warned Lakeville to put guardrails in place first. Cities that waited were rewriting rules under pressure while a project sat on the table. We've seen that play out around here, like when Farmington's data center fight got heated. Lakeville has even been to court over whether a business park site could become one. A judge sided with the city in that data center lawsuit back in May.
Where a Data Center Could Go
Right now, a data center is a "permitted use" in some Lakeville zones. That means it could get built with a normal building permit and staff review.
The new draft changes that. Here's how:
- Special permit required. Data centers become a "conditional use." That means a public hearing at the Planning Commission and a vote by council.
- Only two zones. The I-1 and I-2 industrial districts.
- Gone from Office Park. The OP zone is out entirely.
- No campuses. A "data center campus" means several data center buildings on one site. Think hyperscale. They aren't allowed anywhere.
- 500-foot buffer. Buildings and outdoor equipment have to sit at least 500 feet from County Road 70, from homes and residential zones, and from the city's borders.
The rules would live in a new section of the zoning code, Chapter 39.
Power and Water
Energy use is the first thing a lot of people ask about. Here's the tricky part. City staff and the city attorney say state law doesn't let Lakeville limit how much power a data center uses or what it pays. The city can only regulate transmission lines.
Own a local south metro business?
We help Dakota & Scott County businesses reach local readers. Takes 30 seconds.
Thanks β enjoy the read! π
So the draft makes the builder show their energy plan. How much power will it use at peak? What new power lines would it need? And the builder pays for any new power lines it needs, not the city.
Water works differently. The state DNR gives out water use permits first. Then Lakeville checks every big user against its water system master plan. That plan maps out the whole city's water needs for decades. The industrial park has a set amount of capacity. If a project would use more than that, it doesn't meet the rules.
If the city's water system needs new wells, towers or pipes to serve a data center, the builder pays for those too.
Staff decided not to put a hard cap on data center water use. Instead, the draft does something bigger. Any cooling system has to be air-cooled or use another method that doesn't use water. Planning consultant Daniel Licht said that sidesteps the water question completely. For context, Meta's data center in Rosemount is listed as using air-cooled chillers.
Noise, Generators and Neighbors
Data centers run 24 hours a day. The fans and cooling never stop. So noise got a lot of attention.
- Generators: Backup generators that burn fuel can only run during a power outage. They can't be used to save on power bills.
- Testing: Generator testing is only allowed 9 a.m. to 5 p.m. on weekdays, and only one at a time.
- Low hums: On top of state noise rules, the draft adds limits on low, rumbly sound, the kind you feel as much as hear.
- Quieter at night: Near homes, the limit drops from 60 decibels during the day to 50 overnight.
The draft also covers lights and looks. Outdoor lights have to dim by half from 10 p.m. to 5 a.m. Equipment outside has to be hidden behind at least 14 feet of berms, trees, fences or walls.
How does the city check? Every year, the operator has to turn in a new sound study. If neighbors keep complaining, the city can order one extra study a year. Licht joked that this beats having city staff stand by the road with a borrowed noise meter.
What Happens If It Shuts Down
The new draft also plans for the end. Before it can even get a building permit, the owner has to post money with the city. It's 125% of what it would cost to tear the place down and clean up the site. If the owner walks away, taxpayers don't get stuck with the bill.
If a data center sits unused for 12 months in a row, it counts as shut down. Teardown has to start within a year after that and be done within 18 months of the owner's shutdown notice. Licht said the whole process, from going dark to a cleared site, is meant to take about 30 months at most.
There's also an emergency plan the fire marshal, police and public works review. And an annual report showing the operator is following every rule. If something big changes, like water use jumping way up, the city can reopen the permit.
What Residents Said
Four people spoke. All four said thanks.
Chuck Banks, speaking for the Lakeville Green Coalition, said his group spent months researching noise, water and energy rules. He thanked council and staff for listening and credited Lakeville Friends of the Environment and Debbie Nelson for opening doors. He said the rules would keep a hyperscale data center like the one in Rosemount out of Lakeville.
Patrick Zamponia, whose family has lived in Lakeville about 37 years, called the new draft "significantly stronger" than July's. He liked dropping Office Park, tighter noise rules and the ban on water cooling.
Phil Wilson asked about penalties. Big companies sometimes find it cheaper to pay a fine than follow the rules, he said.
Moises Del Real, who sits on the city's Finance Committee but spoke as a private citizen, asked the city to think long term about water and energy. Will what we allow now compete with things we want later, like a rec center?
So What Are the Penalties?
Licht answered Wilson's question. Any approved data center signs a performance agreement with every condition in it. The city attorney can enforce it. The city can also take away the permit, which means the building can't legally run. And every day of a violation counts as a separate offense the city can take to court.
The Thing the City Can't Require
Mayor Luke Hellier asked if Lakeville could require "community betterment" payments to the city or school district. He said that's becoming common in the industry. The answer was no. Conditions have to tie directly to zoning impacts like noise and light. The mayor's response: "That would be my encouragement to any future councils."
What Council Thinks
Council seemed happy. Wolter called it "a model for how local government is supposed to work." Another council member said usually technology outpaces the rules, but this time it's the other way around.
Council Member Joshua Lee called it "a model ordinance for today." But he wants a version 2.0 next year. A year ago, everyone talked about water cooling. Now it's air and gel cooling, which push out a lot of heat. Lee wants to look at heat islands, rooftop solar and ways to reuse that heat.
The Bottom Line
Lakeville is getting ahead of this one. The draft goes back to the Planning Commission for a formal public hearing, as early as Dec. 3. Then a final draft comes back to council on Dec. 21. If you want to weigh in, that hearing is your shot. Agendas post on the city council page.
If you're curious how other cities handle this, groups like AI Now explain why special permits matter for data centers. And for the bigger local picture, see how Rosemount residents pushed for a pause after a second Meta project.
Frequently Asked Questions
Is someone trying to build a data center in Lakeville?
No. The city says it has no application or proposal, and never has. These rules are meant to be ready ahead of time.
Where could a data center go in Lakeville?
Only in the I-1 and I-2 industrial zones, with special approval. It would also have to sit at least 500 feet from County Road 70, homes, residential zones and the city's borders.
Can Lakeville limit how much power a data center uses?
Not directly. Staff says state law only lets cities regulate transmission lines. The builder does have to show its energy plan.
Will a data center use our drinking water?
The draft requires air cooling or another non-water method. Any project would also be checked against the city's water master plan.
When does this become official?
After a Planning Commission public hearing, likely Dec. 3, council plans a final vote Dec. 21.